1.2.11
Epoxy Injection Adhesive
A low viscosity epoxy resin system pumped under pressure into
cracks.
1.2.12
Rapid-Hardening Repair Material
A combination of rapid-setting cement and aggregate(s) that can develop
sufficient compressive strength at an early age to permit intended use.
1.2.13
Non-Structural Cracks
Cracks that do not affect the load-carrying capacity of the structure.
1.2.14
Structural Cracks
Cracks that affect the load-carrying capacity of the structure.
1.3
UNIT PRICES
**************************************************************************
NOTE: If Section 01270A MEASUREMENT AND PAYMENT is
paragraph title (UNIT PRICES) should be deleted from
this section and the remaining appropriately edited
subparagraphs below should be inserted into Section
01270A. For additional guidance on payment items,
see International Concrete Repair Institute
Guidelines No. 03735 "Guide for Methods of
Measurement and Contract Types for Concrete Repair
Work".
**************************************************************************
NOTE: For small projects where other relevant guide
specifications are not included in the project
specification, insert applicable measurement and
payment paragraphs either here or in Section 01270A.
**************************************************************************
1.3.1
Concrete Removal
**************************************************************************
NOTE: Repeat this bid item and its respective
subparagraphs for each bid item of concrete removal,
renumbering the bid items appropriately. Unit price
bid items should be inserted in paragraph UNIT PRICE
BID ITEMS of Section 01270A MEASUREMENT AND PAYMENT.
Where concrete removal depth is uniform across an
area, measurement and payment may be made on an area
basis, in which case the "ALTERNATE" paragraph may
be used.
**************************************************************************
1.3.1.1
Payment
Payment will be made for costs associated with concrete removal, which
includes preparatory work, removal of concrete and embedded items, and
disposal of debris. Payment will be made at the contract price per cubic
SECTION 03931
Page 14