electrical conduits or other materials, nor for individual voids or
embedded items which are either less than 0.15 cubic meters (five cubic
feet) five cubic feet in volume or 0.10 square meter (one square foot) one
square foot in cross section.
1.3.5.3
Unit of Measure
Unit of measure: cubic meter yard.
1.3.6
Mortar
1.3.6.1
Payment
Payment for [cement-based mortar] [epoxy mortar] [polymer-modified mortar]
[Rapid-Hardening Repair Mortar] will be made at the respective contract
unit prices per cubic meter foot. These payments shall constitute full
compensation for performing the work and shall include the cost of all
labor, equipment and tools, materials and supplies required to complete the
mortar work under this contract; except steel reinforcement, and embedded
parts which are specified to be paid for separately. No measurement and
payment will be made for mortar, as such, which is placed in structures for
which payment is made as a lump sum. No separate payment will be made for
1.3.6.2
Measurement
Measurement of mortar will be made on the basis of the actual volume of
mortar placed, within the limits of work, as indicated on the contract
drawings. Measurement will be made in accordance with paragraph FIELD
MEASUREMENT. No deductions will be made for rounded or beveled edges or
space occupied by metal work, electrical conduits or other materials, nor
for voids or embedded items.
1.3.6.3
Unit of Measure
Unit of measure: cubic meter foot.
1.3.7
Grout
1.3.7.1
Payment
Payment for [cement-based] [epoxy] [polymer-modified] grout will be made at
the respective contract unit prices per cubic meter foot. These payments
shall constitute full compensation for performing the work and shall
include the cost of all labor, equipment and tools, materials and supplies
required to complete the grout work under this contract. No measurement
and payment will be made for grout, as such, which is placed in structures
for which payment is made as a lump sum. No separate payment will be made
1.3.7.2
Measurement
Measurement of grout will be made on the basis of the actual volume of
grout placed, within the limits of work, as indicated on the contract
drawings. Measurement will be made in accordance with paragraph FIELD
MEASUREMENT. No deductions will be made for rounded or beveled edges or
space occupied by metal work, electrical conduits or other materials, nor
for individual voids or embedded items.
SECTION 03931