1.3.3
Drilling and Grouting Dowels and Anchors
1.3.3.1
Payment
Payment will be made for costs associated with drilling holes and grouting
dowels and anchors for anchoring new concrete and for repairs to existing
concrete. The price shall include the cost of furnishing all equipment,
labor, and materials, except dowels and anchors, and all other incidental
costs in connection with completing the item of work as shown and as
specified. Payment for dowels and anchors will be made as specified for
dowels, anchors, and reinforcing steel bars.
1.3.3.2
Measurement
Measurement of drilling holes and grouting dowels and anchors will be made
by the linear meter foot of hole actually drilled and grouted to the depth
indicated. Measurement will be made from the surface of the concrete after
removal or surface preparation and will be made to the nearest 25 mm (inch)
inch. No payment will be made for holes improperly drilled or grouted nor
for repairs required due to damage caused by the drilling and grouting
operations.
1.3.3.3
Unit of Measure
Unit of measure: linear meterfeet.
1.3.4
Dowels and Anchors
Measurement and payment for furnishing and placing dowels, anchors and
reinforcing steel bars for anchorage will be made as specified in Section
03201 STEEL BARS AND WELDED WIRE FABRIC FOR CONCRETE REINFORCEMENT FOR
CIVIL WORKS.
1.3.5
Concrete
Measurement and payment for cement-based concrete will be made as specified
in Section [03300A CAST-IN-PLACE STRUCTURAL CONCRETE][03301A CAST-IN-PLACE
STRUCTURAL CONCRETE FOR CIVIL WORKS][03307 CONCRETE FOR MINOR STRUCTURES].
1.3.5.1
Payment
Payment for [epoxy] [polymer-modified] [fiber-reinforced] concrete will be
made at the respective contract unit prices per cubic meter yard. These
payments shall constitute full compensation for performing the work and
shall include the cost of all labor, equipment and tools, materials and
supplies required to complete the concrete work under this contract; except
steel reinforcement, and embedded parts which are specified to be paid for
separately. No measurement and payment will be made for concrete, as such,
which is placed in structures for which payment is made as a lump sum. No
separate payment will be made for bonding coats or agents.
1.3.5.2
Measurement
Measurement of concrete will be made on the basis of the actual volume of
concrete placed, within the limits of work, as indicated on the contract
drawings. Measurement of concrete placed against the sides of any
excavation without the use of intervening forms will be made only within
the pay lines of the structure shown on the contract drawings. Measurement
will be made in accordance with paragraph FIELD MEASUREMENT. No deductions
will be made for rounded or beveled edges or space occupied by metal work,
SECTION 03931
Page 16