1.2.6.2
Measurement
Water-reducing admixture (WRA) will be measured for payment based upon the
actual volume of concrete containing the admixture and within the pay lines
of the structures, as determined in accordance with the concrete bid items.
1.2.6.3
Unit of Measure
Unit of measure:
cubic meters yards.
1.2.7
High-Range Water-Reducing Admixture (HRWR)
1.2.7.1
Payment
[Payment will be made for costs associated with high-range water-reducing
admixture (HRWR) at the applicable contract unit price per cubic meter yard
of concrete containing water-reducing admixture.] [Payment will be made for
costs associated with high-range water-reducing admixture (HRWR) at the
applicable contract unit cost of concrete containing water-reducing
admixture for:
a.
"Bid Item [_____]a., first [_____] cubic meters yards."
b.
"Bid Item [_____]b., all over [_____] cubic meters yards."]
1.2.7.2
Measurement
High-Range water-reducing admixture (HRWR) will be measured for payment
based upon the actual volume of concrete containing the admixture and
within the pay lines of the structures, as determined in accordance with
the concrete bid items.
1.2.7.3
Unit of Measure
Unit of measure:
cubic meters yards.
1.2.8
[Silica Fume, Dry]
1.2.8.1
[Payment
Payment will be made for costs associated with silica fume, dry, which
includes price batching and recording equipment for dry silica fume used in
the concrete bid items. Payment will be made at the contract price per
kilogram hundredweight of dry silica fume for:
a.
"Bid Item [_____]a., first [_____] kilograms hundredweight."
b.
"Bid Item [_____]b., all over [_____] kilograms hundredweight.]"
1.2.8.2
[Measurement
Silica fume, dry, will be measured for payment based upon the number of
kilograms hundredweight of silica fume used in the concrete, excluding the
amount wasted or used for the convenience of the Contractor. The quantity
to be paid for will be determined by multiplying the weight in kilograms
pounds of silica fume per cubic meter yard by the number of cubic meters
yards of silica fume concrete placed within the pay lines of the structure
as determined in accordance with the concrete bid items, . divided by 100.]
SECTION 03700