Consult the concrete materials design memorandum to
choose the appropriate cementitious materials and
admixtures for measurement and payment.
**************************************************************************
1.2.1
Structure [_____]
**************************************************************************
NOTE: Repeat this lump sum bid item and its
respective subparagraphs for each structure to be
paid for by lump sum, renumbering the bid items
appropriately. Lump sum bid items should be
inserted in paragraph LUMP SUM BID ITEMS of Section
01270A MEASUREMENT AND PAYMENT.
**************************************************************************
1.2.1.1
Payment
Payment will be made for costs associated with operations necessary for
construction of the structure at Station [_____].
1.2.1.2
Unit of Measure
Unit of measure:
lump sum.
1.2.2
Concrete for [_____]
**************************************************************************
NOTE: Repeat this bid item and its respective
subparagraphs for each bid item of concrete,
renumbering the bid items appropriately. Unit price
bid items should be inserted in paragraph UNIT PRICE
BID ITEMS of Section 01270A MEASUREMENT AND PAYMENT.
**************************************************************************
1.2.2.1
Payment
Payment will be made for costs associated with completing the concrete work
for concrete placed in the [_____]. However, these costs will not include
the cost of embedded parts that are specified to be paid for separately.
No payment will be made for concrete, as such, that is placed in structures
of which payment is made as a lump sum.
1.2.2.2
Measurement
Concrete will be measurement for payment based upon the actual volume of
concrete within the pay lines of the structures as indicated on the
drawings. Measurement of concrete placed against the sides of any
excavation without the use of intervening forms shall be made only within
the pay lines of the structure. No deductions shall be made for rounded or
beveled edges, space occupied by metal work, electrical conduits or
reinforcing steel, or for voids or embedded items that are either less than
0.14 cubic meters 5 cubic feet in volume or 0.09 square meter 1 square foot
in cross section.
1.2.2.3
Unit of Measure
Unit of measure:
cubic meters yards.
SECTION 03301A