Officer (HASO) and the members of the drill crew. The CPC may perform the
responsibilities of the HASO if properly qualified.
1.6.4
Field Sampling and Laboratory Testing Plan
Describe field
sampling methods and quality control procedures. Identify
laboratory and
Sample reports
shall show sample identification for location, date, time,
sample method,
identification
of laboratory, and quality control procedures.
1.6.5
Treatment Facility Permit
Verification that the proposed treatment facility is permitted to accept
the contaminated materials specified, prior to the start of excavation.
1.6.6
Well Development Report
Provide report, containing the following data [for each well]: project
name and location, well designation, date and time of well installation,
date and time of well development, static water level from top of well
casing before development and 24 hours after development, field
measurements of pH, temperature, and specific conductivity, depth of well
from top of casing to bottom of well, screen length, description of
development methodology size/capacity of pump or bailer, pumping rate, and
recharge rate.
1.6.7
Well Construction Permit
Submit a completed permit application and a proposed method of construction
to the appropriate state agency prior to construction of the well.
Construction of the well[s] will not be allowed until an approved Well
Construction Permit has been submitted to the Contracting Officer.
1.6.8
Shipment Manifests
Copies of manifests and other documentation required for shipment of waste
materials within 24 hours after removal of waste from the site. Shipment
manifests shall be signed by the Contracting Officer.
1.6.9
Delivery Certificates
Verification that the wastes were actually delivered to the approved
treatment facility, within 7 days of shipment.
1.6.10
Treatment and Disposal Certificates
Verification that the wastes were successfully treated and remediated to
the levels specified herein.
PART 2
PRODUCTS
2.1
WELL CASING
**************************************************************************
NOTE: Selection of casing and screen material type
is critical to both the life of the well and the
accuracy of the sampling data. Analysis of the
SECTION 02525N
Page 8