Field Sampling and Laboratory Testing Plan; G
Treatment facility permit
Installation Survey Report
Well Development Report
Borehole Analysis Report
SD-11 Closeout Submittals
Well Construction Permit
Shipment manifests
Delivery certificates
Treatment and disposal certificates
1.5
DELIVERY, STORAGE, AND HANDLING
Deliver materials in an undamaged condition. Unload and store with minimal
handling. Store materials in on-site enclosures or under protective
coverings. Store [plastic piping and jointing materials, and] rubber
gaskets under cover, out of direct sunlight. Store materials off the
ground. Keep insides of pipes and fittings free of dirt and debris.
Replace defective or damaged materials with new materials.
1.6
QUALITY ASSURANCE
1.6.1
Required Drawings
Submit well construction drawings showing components and details of well
casing, well screen, filter pack, annular seal, and associated items.
Drawings shall be prepared by a State certified professional geologist or
hydrogeologist, or by a State registered professional civil engineer,
hereafter referred to as the Contractor's Professional Consultant (CPC).
Drawings shall be sealed.
1.6.2
Well Drilling/Development Material Handling Plan
A material handling plan shall be furnished by the Contractor 15 days prior
to initiation of the work that describes phases of dealing with the
potentially contaminated soil and groundwater, including the following: a
schedule to be employed in the well drilling and development stages, a
sequence of operations, the method of drilling and development, material
hauling, proposed equipment, handling of the contaminated materials, soil
and water testing requirements, and safety precautions and requirements.
1.6.3
Health and Safety Plan (HASP)
Describe safety precautions for each phase of the project as specifically
related to handling of soil and water removed during well drilling and
development operations. Identify appropriate requirements of 29 CFR 1910
and EM 385-1-1. Identify safety equipment and procedures to be available
and used during the project. Furnish the name and qualifications based on
education, training, and work experience of the proposed Health and Safety
SECTION 02525N