1.2.9.3
Unit of Measure
Unit of measure:
bags (42 kg 94 lbs).
1.2.10
Redrilling Grouted Holes
**************************************************************************
NOTE: This payment item will be deleted when
watertightness testing is not required.
**************************************************************************
1.2.10.1
Payment
Payment will be made for costs associated with Redrilling Grouted Holes.
1.2.10.2
Measurement
Redrilling Grouted Holes will be measured for payment to the nearest 300 mm
foot, based upon the meters linear feet of hole actually drilled in grout
in accordance with the specifications.
1.2.10.3
Unit of Measure
Unit of measure:
meter linear foot.
1.3
DEFINITIONS
The following definitions are in addition to those given in PTI 4, Section
2.0:
Anchored Structure - The wall, foundation or other structure to which the
anchor is to transfer force.
Demonstration Test Anchor - An anchor which is performance tested to verify
design assumptions and installation practices.
1.4
SUBMITTALS
**************************************************************************
NOTE: Submittals must be limited to those necessary
for adequate quality control. The importance of an
item in the project should be one of the primary
factors in determining if a submittal for the item
should be required.
A "G" following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
SECTION 02490
Page 13