Silica fume manufacturer's representative]
Prestressing steel
Portland cement
Concrete mix design
Reinforcing steel
[
Rubbing surface]
Bolts, nuts, and washers
1.3
REQUIREMENTS
1.3.1
Piling Lengths and Quantity
Provide prestressed pretensioned concrete piles. Base bids upon the
number, size, and length of piles as indicated. Adjustments in the
contract price will not be made for cutting off piles or for broken,
damaged, or rejected piles.
1.3.2
Piles
Prepare in accordance with ACI SP-66. Indicate placement of reinforcement
including tendons. Indicate location of special embedded or attached
lifting devices, employment of pick-up points, support points other than
pick-up points, and any other methods of pick-up. [Provide certification
of a professional engineer registered in any jurisdiction, that layout and
details of reinforcement and tendons conform with that shown on the
structural design drawings.]
1.3.3
Driving Helmets, Capblocks, and Pile Cushions
Show details of driving helmets, capblocks, and pile cushions.
Submit 2
weeks prior to [test] pile installation.
1.4
QUALITY ASSURANCE
1.4.1
Quality Control Procedures
Submit [_____] copies of precasting manufacturer's quality control
procedures established in accordance with PCI MNL-116.
[1.4.1.1
Curing of Piles
Submit proposed materials and methods.
]1.4.2
Silica Fume Manufacturer's Representative
Provide statement that the manufacturer's representative will be present at
plant to ensure proper mix, including high range water reducer (HRWR), and
batching methods.
1.4.3
Aggregates
Prior to pile fabrication, submit certified test reports for the following
SECTION 02395
Page 8