c.
Establish level of workmanship and verify that it meets minimum
acceptable workmanship standards. Compare with required sample
panels as appropriate.
d.
Resolve all differences.
e.
Check safety to include compliance with and upgrading of the
safety plan and activity hazard analysis. Review the activity
analysis with each worker.
f.
The Government shall be notified at least [_____] hours in advance
of beginning the initial phase. Separate minutes of this phase
shall be prepared by the CQC System Manager and attached to the
daily CQC report. Exact location of initial phase shall be
indicated for future reference and comparison with follow-up
phases.
g.
The initial phase should be repeated for each new crew to work
onsite, or any time acceptable specified quality standards are not
being met.
3.6.3
Follow-up Phase
Daily checks shall be performed to assure control activities, including
control testing, are providing continued compliance with contract
requirements, until completion of the particular feature of work. The
checks shall be made a matter of record in the CQC documentation. Final
follow-up checks shall be conducted and all deficiencies corrected prior to
the start of additional features of work which may be affected by the
deficient work. The Contractor shall not build upon nor conceal
non-conforming work.
3.6.4
Additional Preparatory and Initial Phases
Additional preparatory and initial phases shall be conducted on the same
definable features of work if: the quality of on-going work is
unacceptable; if there are changes in the applicable CQC staff, onsite
production supervision or work crew; if work on a definable feature is
resumed after a substantial period of inactivity; or if other problems
develop.
3.7
TESTS
3.7.1
Testing Procedure
The Contractor shall perform specified or required tests to verify that
control measures are adequate to provide a product which conforms to
contract requirements. Upon request, the Contractor shall furnish to the
Government duplicate samples of test specimens for possible testing by the
Government. Testing includes operation and/or acceptance tests when
specified. The Contractor shall procure the services of a Corps of
Engineers approved testing laboratory or establish an approved testing
laboratory at the project site. The Contractor shall perform the following
activities and record and provide the following data:
a.
Verify that testing procedures comply with contract requirements.
b.
Verify that facilities and testing equipment are available and
SECTION 01451A
Page 12