Experience Matrix
Area
Qualifications
yr experience
h.
Occupied family housing
Person, customer relations
type, coordinator experience
i.
Concrete, Pavements and Soils
Materials Technician with
2 yrs experience for the
appropriate area
j.
Testing, Adjusting and Balancing
Specialist must be a member
(TAB) Personnel
of AABC or an experienced
technician of the firm
certified by the NEBB.
k.
Design Quality Control Manager
Registered Architect
or Professional Engineer
3.4.4
Additional Requirement
In addition to the above experience [and] [and/or] education requirements
the CQC System Manager shall have completed the course entitled
"Construction Quality Management For Contractors". This course is
periodically offered at [_____].
3.4.5
Organizational Changes
The Contractor shall maintain the CQC staff at full strength at all times.
When it is necessary to make changes to the CQC staff, the Contractor shall
revise the CQC Plan to reflect the changes and submit the changes to the
Contracting Officer for acceptance.
3.5
SUBMITTALS AND DELIVERABLES
Submittals, if needed, shall be made as specified in Section 01330
SUBMITTAL PROCEDURES. The CQC organization shall be responsible for
certifying that all submittals and deliverables are in compliance with the
contract requirements. When Section 15995A COMMISSIONING OF HVAC SYSTEMS
are included in the contract, the submittals required by those sections
shall be coordinated with Section 01330 SUBMITTAL PROCEDURES to ensure
adequate time is allowed for each type of submittal required.
3.6
CONTROL
Contractor Quality Control is the means by which the Contractor ensures
that the construction, to include that of subcontractors and suppliers,
complies with the requirements of the contract. At least three phases of
control shall be conducted by the CQC System Manager for each definable
feature of the construction work as follows:
3.6.1
Preparatory Phase
This phase shall be performed prior to beginning work on each definable
feature of work, after all required plans/documents/materials are
approved/accepted, and after copies are at the work site. This phase shall
SECTION 01451A