NOTE: Use this on PACDIV projects.
**************************************************************************
[ Establish and maintain a QC program as described in this section. This QC
program is a key element in meeting the objectives of NAVFAC Commissioning.
The QC program consists of a QC Organization, QC Plan, QC Plan Meeting(s),
a Coordination and Mutual Understanding Meeting, QC meetings, three phases
of control, submittal review and approval, testing, completion inspections,
and QC certifications and documentation necessary to provide materials,
equipment, workmanship, fabrication, construction and operations which
comply with the requirements of this Contract. The QC program shall cover
on-site and off-site work and shall be keyed to the work sequence. No
construction work or testing may be performed unless the QC Manager is on
the work site. The QC Manager shall report to the Project Superintendent.
The QC Manager, Project Superintendent and Project Manager must work
together effectively. Although the QC Manager is the primary individual
responsible for quality control, all individuals will be held responsible
for the quality of work on the job.]
1.4.1
Commissioning
Commissioning is a systematic process of ensuring that all building systems
meet the requirements and perform interactively according to the Contract.
The QC Program is a key to this process by coordinating, verifying and
documenting measures to achieve the following objectives:
a. Verify that the applicable equipment and systems are installed in
accordance with the Contact and according to the manufacturer's
recommendations.
b. Verify and document proper performance of equipment and systems.
c. Verify that O&M documentation is complete.
d. Verify that the Government's operating personnel are adequately
trained.
e. Document the successful achievement of the commissioning objectives
listed above.
1.4.2
Acceptance of the Construction Quality Control (QC) Plan
Acceptance of the QC Plan is required prior to the start of construction.
The Contracting Officer reserves the right to require changes in the QC
Plan and operations as necessary, including removal of personnel, to ensure
the specified quality of work. The Contracting Officer reserves the right
to interview any member of the QC organization at any time in order to
verify the submitted qualifications. All QC organization personnel shall
be subject to acceptance by the Contracting Officer. The Contracting
Officer may require the removal of any individual for non-compliance with
quality requirements specified in the Contract.
1.4.3
Preliminary Construction Work Authorized Prior to Acceptance
The only construction work that is authorized to proceed prior to the
acceptance of the QC Plan is mobilization of storage and office trailers,
temporary utilities, and surveying.