NOTE: Include the following three paragraphs when
the project includes the requirement for Phased
Construction.
**************************************************************************
[e.
Phase Start Milestone: The Contractor shall include as the first
activity for a project phase, an activity named "Start Phase X",
where "X" identifies the phase of work. The "Start Phase X"
activity shall have an unconstrained start date equal to the date
of the Phase NTP. This unconstrained start date is not a release
from contractually required start dates, but is left unconstrained
to allow the schedule logic to calculate without hindrance.
f.
End Phase Milestone: The Contractor shall include as the last
activity in a project phase, an activity named "End Phase X" where
"X" identifies the phase of work. The "End Phase X" activity
shall have an unconstrained late finish date equal to the contract
phase completion date. This unconstrained completion date is not
a release from contractually required finish dates, but is left
unconstrained to allow the schedule logic to calculate without
hindrance.
g.
Early Phase Completion: If the Contractor expects to finish prior
to the contract phase completion date, the milestone will show an
early finish date equal to the Contractor's early finish date.
The name of the activity will be "Early Phase Completion" and will
have an unconstrained date representing the Contractor's early
phase completion date.]
1.6.2.3
Activity Identification (ID) and Description
a.
Standard Activity ID Dictionary: The Contractor shall submit the
alphanumeric coding scheme for Schedule Activity Numbers that
shall be used throughout the project. The coding scheme submitted
shall list the values for each activity code and translate those
values into project specific designations. Code length shall not
exceed [10][_____] characters. Once accepted, the coding scheme
will be used for the duration of the project.
b.
Activity Description: Each activity shall have a narrative
description consisting of a Verb or work function (e.g.; form,
pour, excavate), an Object (e.g.; slab, footing, under floor
plumbing), and Area (e.g.; 3rd floor, northeast quadrant,
basement).
1.6.2.4
Activity Code Dictionary and Values
The Contractor shall establish the activity codes identified in this
specification. The codes will have values assigned that will allow the
scheduling program to sort, select, group and organize the activities in
the schedule. Activity codes include, but are not limited to, the
following codes:
**************************************************************************
NOTE: Include the following paragraph when the
project includes the requirement for Phased
Construction.