Submission of data from another software system where data conversion
techniques or software is used to import into Primavera's scheduling
software is not acceptable and will be cause for rejection of the submitted
schedule.
1.5
QUALIFICATIONS
**************************************************************************
NOTE: The requirement for a full time scheduler
will be used very infrequently and only on projects
that are large and complex enough to warrant the
additional expense. A part time scheduler can be
specified (and part time defined) when complexity
and size does not warrant a full time scheduler and
the ROICC does not want emphasis of the duty left to
the discretion of the Contractor. Lastly, the
office may choose to not designate full or part time
and leave the emphasis of the duty to the
Contractor. Before editing the following paragraph,
coordinate with the ROICC Office.
**************************************************************************
The Contractor shall designate a [full time][part time] Scheduler that will
be responsible for the development, preparation, and maintenance of an
accurate, computerized Network Analysis Schedule. [Full time is defined as
the scheduler being on-site during normal work hours to perform on-site
coordination, attending project meetings, and updates. The Scheduler shall
have no other duties than scheduling for this contract.] [Part time is
defined as the Scheduler performing [on-site] coordination, attending
project meetings, and updates for [_____] hours per work week. ]The
Scheduler shall have previously developed, created and maintained at least
[2][_____] previous computerized schedules of similar size and complexity
of this contract. A resume outlining the qualifications of the Scheduler
and their SureTrak or P3 training certificate from an authorized Primavera
trainer shall be submitted for acceptance to the Contracting Officer. If
at a later date, the Contracting Officer considers the Contractor's
Scheduler to be incompetent or objectionable, the Contractor will propose a
new Scheduler, meeting the qualification requirements. Payments will not
be processed until an acceptable Scheduler is provided.
1.6
NETWORK SYSTEM FORMAT
reports.
1.6.1
Diagrams
Show the order and interdependence of activities and the sequence in which
the work is planned to be accomplished. The basic concept of the network
analysis diagram will be followed to show how the start of a given activity
is dependent on the completion of preceding activities and how its
completion restricts or restrains the start of following activities.
Activity durations shall not be resource-driven, activities shall start
according to network logic and finish when its duration has elapsed.
Diagrams shall be [organized by [Work Phase][Area Code],] sorted by Early
Start Date and will show a continuous flow from left to right with no logic
(relationship lines) from right to left. With the exception of the
Contract Award, Start Project and End Project milestone activities, no
activities will be open-ended; each activity will have predecessor and
SECTION 01321N
Page 7