choices or locations where text must be supplied by
the designer.
**************************************************************************
**************************************************************************
NOTE: This guide specification requires project
costs to be loaded into the schedule and assigned to
activities. When using this section, delete the
requirement for "Schedule of Prices" in Section
01200 "Price and Payment Procedures".
**************************************************************************
PART 1
GENERAL
1.1
DESCRIPTION
**************************************************************************
NOTE: Edit the following paragraph as applicable
for Design-Build or Design-Bid-Build contracts.
**************************************************************************
The network analysis system shall consist of the network analysis schedule
(diagram) and associated reports. The scheduling of all[ design,]
procurement and construction shall be the responsibility of the Contractor.
[All design and construction][Construction] increments will be
interrelated on a single schedule that represents the entire project
duration from Contract Award to the Contract Completion Date. Schedule
updates will build upon each other and will include [design and
]construction increments as they are detailed, submitted and accepted.
Submission of progress and revision data will be used to measure work
progress, aid in the evaluation for requests for time extensions, and to
of network calculation shall be used to generate the project schedule and
will utilize the Precedence Diagram Method (PDM) to satisfy both time and
cost applications. All progress payment amounts will be derived from and
tied to the cost-loaded schedule activities.
For consistency, when scheduling software terminology is used in this
specification, the terms in Primavera's scheduling programs are used.
Primavera Project Planner, P3, Primavera Project Manager, SureTrak and
PrimeContract are registered trademarks or service marks of Primavera
Systems, Inc. Adobe and Acrobat are registered trademarks of Adobe Systems
Incorporated.
1.2
SUBMITTALS
**************************************************************************
NOTE: Submittals must be limited to those necessary
for adequate quality control. The importance of an
item in the project should be one of the primary
factors in determining if a submittal for the item
should be required.
A "G" following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
SECTION 01321N
Page 4