courtesy and are not conditions of Government acceptance; but are for the
general conformance with established industry schedule concepts.
1.3.1
Schedule Acceptance Prior to Start of Work
[Unless stipulated otherwise as part of the Contract Award, design work may
not be started prior to submittal and acceptance of the Design Network
Analysis Schedule by the Government. Acceptance of the Design NAS will be
a condition precedent to processing any pay requests submitted by the
Contractor. ]The Baseline Network Analysis Schedule described in the
paragraph entitled "Baseline Network Analysis Schedule" must be submitted
and accepted by the Government before the Contractor will be allowed to
start work on the construction stage(s) of the contract. Examples of
construction stages are, but not limited to; demolition, site work,
temporary work for construction, etc.
1.3.2
Acceptance
a.
[When the Design Network Analysis Schedule is submitted and
accepted by the Contracting Officer it will be considered the
"Baseline Network Analysis Schedule for Design". The Design
Network Analysis Schedule shall be updated at least monthly or
submitted as part of the design submittals, whichever occurs
first. ]When the Construction Network Analysis Schedule is
submitted and accepted by the Contracting Officer, it will then be
considered the "Baseline Network Analysis Schedule". The Baseline
Network Analysis Schedule will then be used by the Contractor for
planning, organizing, and directing the work; reporting progress;
and requesting payment for work accomplished. The schedule will
be updated monthly by the Contractor and submitted monthly with
the progress pay request to reflect the current status of the
work. Submittal and acceptance of the [Baseline Network Analysis
Schedule for Design and ]Baseline Network Analysis Schedule and
accurate updated schedules accompanying the pay requests are both
conditions precedent to processing pay requests. Only bonds will
be paid prior to acceptance of the Baseline Schedule(s).
b.
Submittal of the Baseline Network, and subsequent schedule
updates, will be understood to be the Contractor's certification
that the submitted schedule meets all of the requirements of the
Contract Documents, represents the Contractor's plan on how the
work will be accomplished, and accurately reflects the work that
has been accomplished and how it was sequenced (as-built logic).
1.4
SOFTWARE
**************************************************************************
NOTE: Contact the Administering ROICC Office to
determine which software will be used on the
project.
**************************************************************************
The scheduling software that will be utilized by the Government on this
project is [SureTrak by Primavera Systems, Inc.][Primavera Project Planner
(P3) by Primavera Systems, Inc.]. Notwithstanding any other provision in
the contract, schedules submitted for this project must be prepared using
either Primavera P3 or Primavera SureTrak (files saved in Concentric P3
format). The Contractor shall provide electronic files saved in a format
that is compatible with the Contracting Officer's current software version.
SECTION 01321N
Page 6