b. The infrastructure and rough-in provided by the facility construction
project are generically designed to accommodate the installation of typical
systems available in the marketplace. This includes cable trays, conduits,
boxes, grounding system and buss bars, and all primary power wiring, as
indicated in the facility construction project contract documents.
c. If the provided system requires any infrastructure or rough-in, in
addition to or different from what has been provided as part of the
facility construction project contract, then the NCAV System Contractor
shall provide all such additional infrastructures and rough-in at no
additional cost to the Government.
d. Provide trim plates as required to adapt faceplates to the boxes
provided by the facility construction project at no additional cost to the
Government.
3.3.7
Infrastructure and Rough-in: Existing Facility
**************************************************************************
NOTE: If the NCAV System is to be procured by the
Government directly from a system Contractor for
installation as a replacement system in an existing
facility, and not associated in any way with a
facility construction project (new, addition or
renovation), then include this paragraph.
**************************************************************************
a. Installation of the system shall utilize existing [cable trays,]
conduits, boxes, grounding system and buss bars, and all primary power
wiring to the maximum extent possible, provided these items accommodate the
installation and operation of the system as specified in this Section.
b. If the provided system requires any infrastructure or rough-in that is
in addition to, or different from, available existing conditions, then the
NCAV System Contractor shall provide all such additional infrastructures
and rough-in at no additional cost to the Government. The NCAV System
Contractor shall be responsible for any costs associated with the
installation of these items by Others.
c. Provide trim plates as required to adapt faceplates to existing boxes
at no additional cost to the Government.
d. Completely remove and discard all existing system cabling that is not
being reused as part of the NCAV System being installed.
e. Completely remove all existing systems equipment that is not being
reused as parts of the NCAV System being installed, and dispose of the
equipment as directed by the Contracting Officer.
3.4
APPLICATION
3.4.1
AC Power Connections
**************************************************************************
NOTE: If the NCAV System is to be installed in a
stand-alone clinic facility that does not have
emergency power, delete this paragraph.
**************************************************************************
SECTION 16731A