application is not a prime power application.
Provide plan and elevation drawings of the remote
panels for prime power applications, depicting
specific devices, instrument, and meters, including
layouts. Edit the table to include all required
devices. Delete optional devices that are not
required for the application. Delete all columns
except the first column and the appropriate
reference column (always delete the "MFG. Offering"
column). Add any necessary parameters to define
devices required. A fuel meter display should be
added for prime rated applications. A fuel header
pressure display should be added for prime rated
applications. Delete the pyrometer devices for sets
smaller than 200 kW. kWh, kVAR, power factor,
meters and reverse power indication may be added as
required.
The following instruments may be added as required.
Indicating VAR meter. Power-factor meter,
indicating. (Specify one of these. They are
normally used only for prime applications, however
can be specified for standby units as required.)
Indicating wattmeter. (Normally used only for prime
applications, however can be specified for standby
units as required.
Totalizing Kilowatt-hour meter with 15 or 30 minute
demand register. (Normally used only for prime
applications, however can be specified for standby
units as required.)
Recording Kilowatt-hour/demand meter. (Normally
used only for prime applications, however can be
specified for standby units as required.)
The 15-minute demand register is preferred to the
30-minute register in most cases, because it permits
more accurate timing of facility peak load
occurrence.
Delete Frequency and Volt meters if a Synchronizing
Panel is provided.
**************************************************************************
A local panel shall be provided with devices [as indicated] [in accordance
with [NFPA 110 level [1] [2]]] [and as follows] mounted [either on or
adjacent to the engine generator set] [as indicated]. A remote control
panel shall be provided [with devices as indicated] [fully redundant to the
Device/Condition/
Corps
NFPA 110
NFPA 110
MFG
Function
Requirement
Level 1
Level 2
Offering
Genset Status & Metering
Genset supplying load
CP VA
CP VAO
CP VAO