3.1.11.3
Inter-Rack and Inter-Tier Cables
Provide flexible, welding type cable for all inter-rack and inter-tier
connections. Number and size shall be as indicated. Battery cables shall
have a long bending radius to avoid excessive stress at the point of
termination.
3.1.12
UPS Spare Parts and Manuals
**************************************************************************
NOTE: Three (3) volumes of UPS maintenance manuals
are provided as part of the UPS package. These
manuals are not commercially available and contain
proprietary information. Additional manuals must be
procured by NFESC ECDet, Code 65.
**************************************************************************
are shipped with the UPS equipment. Perform inventory and store these
items until notified by the Contracting Officer.
3.2
UPS TECHNICAL REPRESENTATIVE
**************************************************************************
NOTE: The UPS manufacturer's technical
representative will inspect the completed UPS and
package, and at no additional cost to the activity.
The representative's visit to the site must be
scheduled by NFESC ECDet, Code 65. If the station
or Contractor requests UPS technical
representative's services without notifying Code 65,
they may incur additional expenses.
**************************************************************************
Contractor shall notify Contracting Officer in writing at least 45 calendar
days prior to completion of the UPS system installation. At this time the
Contracting Officer, via NFESC ECDet, Code 65, will schedule the UPS
manufacturer's technical representative to inspect the completed
installation. The UPS technical representative will provide 15 days of
service including five days of instruction for activity personnel. The
following items shall be completely installed by the Contractor and be
operational prior to the arrival of the UPS representative for inspection,
unit start-up and testing:
a.
Ventilation equipment in the UPS and battery rooms.
b.
Battery [racks][cabinets] and cells. Cells shall not be filled
with electrolyte until directed by the Contracting Officer. This
is not applicable for maintenance free battery.
c.
Battery connections including cell-to-cell, tier-to-tier, and
rack-to-rack connections, with correct polarity;
d.
DC power and control connections between UPS and battery circuit
breaker, with correct polarity;
e.
with correct polarity;
SECTION 16262N
Page 10