Submit drawings for [UPS] and [battery] installation.
SD-03 Product Data
Inter-rack and inter-tier cables; G
Control cable; G
Cable lugs; G
1.4
DELIVERY, STORAGE, AND HANDLING
1.4.1
Government-Furnished Equipment (GFE)
The Government will furnish various components and equipment listed in
article entitled "GOVERNMENT-FURNISHED MATERIAL" for installation by the
Contractor.
[1.4.2
Pick-Up
The GFE will be available on [_____]. Contractor shall pickup, transport
form [_____], unload, unpack and install all GFE. The Contractor shall
notify Contracting Officer [_____] calendar days in advance of the date the
GFE is required for installation. The GFE shall be unpacked by Contractor
in the presence of Contracting Officer to determine damage or missing
parts. Contractor shall be responsible for damages sustained by the
materials and equipment after this inspection. UPS equipment is heavy and
easily damaged. Do not bump or bounce equipment at any time. When
lifting, do not tip beyond 0.087 radians 5 degrees.
][1.4.3
Delivery
Activity will receive, store and deliver the GFE to jobsite. Contractor
shall unload, unpack, and install GFE. Notify Contracting Officer [_____]
calendar days prior to when delivery on the site is required. GFE shall be
unpacked in the presence of Contracting Officer to determine damage or
missing parts. Contractor shall be responsible for damage sustained by the
materials and equipment after this inspection. UPS equipment is heavy and
easily damaged. Do not bump or bounce equipment at any time. When
lifting, do not tip beyond 0.087 radians 5 degrees.
]PART 2
PRODUCTS
2.1
CONTRACTOR FURNISHED MATERIAL AND EQUIPMENT
Materials, equipment, and devices not specifically indicated or specified
to be Government Furnished-Contractor Installed, shall be Contractor
Furnished-Contractor Installed (CFCI). Such equipment required to provide
the completely operable UPS installation includes, but is not necessarily
limited to, conduit, conduit fittings, insulated conductors, compression
lugs, cable trays, supports, fasteners, and other such items.
2.2
GOVERNMENT-FURNISHED MATERIAL
The Government will furnish the following components of the UPS system:
**************************************************************************
NOTE: This information may be obtained from NFESC
ECDet, Code 65.
SECTION 16262N
Page 6