For HVAC System:
[_____]
Checklist Item
Q
M
E
T
C
D
O
U
Installation
a.
As-built shop drawings submitted.
___ ___
X
X
___ ___ ___ ___
b.
Layout of control panel matches drawings.___ ___
X
X
___ ___ ___ ___
c.
Framed instructions mounted in or near
control panel.
___ ___
X
X
___ ___ ___ ___
d.
Components properly labeled (on inside and
outside of panel).
___ ___
X
X
___ ___ ___ ___
e.
Control components piped and/or wired to
each labeled terminal strip.
___ ___
X
X
___ ___ ___ ___
f.
EMCS connection made to each labeled
terminal strip as shown.
___ ___
X
X
___ ___ ___ ___
g.
Control wiring and tubing labeled at all
terminations, splices, and junctions.
___ ___
X
X
___ ___ ___ ___
h.
Shielded wiring used on electronic sensors.__ __
X
X
___ ___ ___ ___
i.
Air dryer installed as specified.
___ ___
X
X
___ ___ ___ ___
j.
Water drain installed as specified.
___ ___
X
X
___ ___ ___ ___
Main Power and Control Air
a.
110 volt AC power available to panel.
___ ___ ___
X
___ ___ ___ ___
b.
138 kPa gauge (20 psig) 20 psig
___ ___
X
X
___ ___ ___ ___
a.
Report submitted.
___ ___
X
___ ___ ___ ___ ___
SECTION 15995A
Page 30