TAB Verification[; G][; G, [_____]]
Proposed date and time to begin the TAB Verification, submitted
with the TAB Report.
SD-06 Test Reports
Design Review Report[; G][; G, [_____]]
A copy of the Design Review Report, no later than [14] [_____]
days after approval of the TAB Firm and the TAB Specialist.
Systems Readiness Check[; G][; G, [_____]]
A copy of completed checklists for each system, each signed by
the TAB Specialist, at least [7] [_____] days prior to the start
of TAB Execution. All items in the Systems Readiness Check Report
shall be signed by the TAB Specialist and shall bear the seal of
the Professional Society or National Association used as the TAB
Standard.
TAB Report[; G][; G, [_____]]
[Three] [_____] copies of the completed
TAB Reports, no later
that [7] [_____] days after the execution
of TAB. All items in
the TAB Report shall be signed by the TAB
Specialist and shall
bear the seal of the Professional Society
or National Association
used as the TAB Standard.
TAB Verification Report[; G][; G, [_____]]
[Three] [_____] copies of the completed TAB Verification Report,
no later that [7] [_____] days after the execution of TAB
Verification. All items in the TAB Verification Report shall be
signed by the TAB Specialist and shall bear the seal of the
Professional Society or National Association used as the TAB
Standard.
SD-07 Certificates
Ductwork Leak Testing
A written statement signed by the TAB Specialist certifying that
the TAB Specialist witnessed the Ductwork Leak Testing, it was
successfully completed, and that there are no known deficiencies
related to the ductwork installation that will prevent TAB from
producing satisfactory results.
TAB Firm[; G][; G, [_____]]
Certification of the proposed TAB Firm's qualifications by
either AABC, NEBB, or TABB to perform the duties specified herein
and in other related Sections, no later than [21] [_____] days
after the Notice to Proceed. The documentation shall include the
date that the Certification was initially granted and the date
that the current Certification expires. Any lapses in
Certification of the proposed TAB Firm or disciplinary action
taken by AABC, NEBB or TABB against the proposed TAB Firm shall be
described in detail.