Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control
approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] The following shall be submitted in accordance with Section
01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
TAB Schematic Drawings and Report Forms[; G][; G, [_____]]
[Three] [_____] copies of the TAB Schematic Drawings and Report
Forms, no later than [21] [_____] days prior to the start of TAB
SD-03 Product Data
TAB Related HVAC Submittals
A list of the TAB Related HVAC Submittals, no later than [7]
[_____] days after the approval of the TAB Specialist.
TAB Procedures[; G][; G, [_____]]
Proposed procedures for TAB, submitted with the TAB Schematic
Drawings and Report Forms.
Calibration
List of each instrument to be used during TAB, stating
calibration requirements required or recommended by both the TAB
Standard and the instrument manufacturer and the actual
calibration history of the instrument, submitted with the TAB
Procedures. The calibration history shall include dates
calibrated, the qualifications of the calibration laboratory, and
the calibration procedures used.
Systems Readiness Check
Proposed date and time to begin the Systems Readiness Check, no
later than [7] [_____] days prior to the start of the Systems
Readiness Check.
TAB Execution[; G][; G, [_____]]
adjustments, etc., for the TAB Report, submitted with the Systems
Readiness Check Report.