all mill scale and rust. However, the surfaces shall be cleaned to remove
all grease and other foreign matter. Paint shall not be applied when the
temperature is below 10 degrees C 50 degrees F or above 32 degrees C 90
degrees F.
2.11.4
Equipment Coating
Equipment and component items, when fabricated from ferrous metal, shall be
factory finished with the manufacturer's standard finish if located within
buildings. Items located outside shall have weather-resistant finishes
that will withstand 500 hours of exposure to the salt-spray test specified
in ASTM B 117, using a 20 percent sodium chloride solution. This test may
be performed on test specimens coated and finished in the same manner as
the actual equipment. Immediately after the test, the specimens shall show
no sign of blistering, wrinkling, cracking, or loss of adhesion and no sign
of rust beyond 3 mm 1/8 inch on either side of the scratch mark.
2.12
FACTORY TESTS
Initial capacity and performance tests of factory-assembled boiler
components shall be conducted at the manufacturer's plant. Any material or
equipment rejected shall be either repaired or replaced before installation.
PART 3
EXECUTION
3.1
INSTALLATION
**************************************************************************
NOTE: All pertinent piping and related equipment
supports will be designed for seismic forces as
specified in subparagraph Support Steel below.
**************************************************************************
Equipment and material shall be installed as indicated and in accordance
with manufacturer's instructions. A manufacturer's representative
experienced in installation of this type of boiler, shall supervise the
erection of the boiler and associated equipment.
3.1.1
Piping
Unless otherwise specified, pipe and fittings shall conform to Section 02554
EXTERIOR ABOVEGROUND STEAM DISTRIBUTION.
3.1.2
Field Painting
**************************************************************************
NOTE: Where identification of piping is required by
the using service, this paragraph will be amplified
to include appropriate requirements either directly
or by reference to a separate section. Air Force
requirements are covered in AFM 88-15.
**************************************************************************
cleaned, prepared, and painted as specified in Section 09900 PAINTS AND
COATINGS. All exposed pipe covering shall be painted as specified in
Section 09900 PAINTS AND COATINGS. Aluminum sheath over insulation shall
not be painted.