following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control
approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] The following shall be submitted in accordance with Section
01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Energy Recovery System
Installation
material, including manufacturer's descriptive and technical
literature, performance charts and curves, catalog cuts, drawings,
piping and wiring drawings, schematic diagrams, and any other
details required to demonstrate that the system has been
coordinated and will properly function as a unit. Drawings shall
show proposed layout and anchorage of equipment and appurtenances,
and equipment relationship to other parts of the work including
clearances required for maintenance and operation.
SD-03 Product Data
Calculations
walls, roof, foundations, and other features for specialty type of
construction, with design data for lateral forces that may be
encountered due to wind loads and seismic zone forces.
Welding Procedures and Qualifications
A copy of qualified procedures and a list of names and
Spare Parts
Spare parts data for each item of equipment provided, as
specified.
Posted Instructions
Proposed diagrams, instructions, and other sheets, prior to
Performance Tests[; G][; G, [_____]]
A proposed performance test procedure, 30 days prior to the