considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control
approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] The following shall be submitted in accordance with Section
01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Drawings
Drawings provided in adequate detail to demonstrate compliance
with contract requirements, as specified.
SD-03 Product Data
Materials and Equipment
Manufacturer's standard catalog data, at least [5 weeks] [_____]
prior to the purchase or installation of a particular component,
highlighted to show material, size, options, performance charts
and curves, etc. in adequate detail to demonstrate compliance with
contract requirements. Data shall include manufacturer's
vibration isolation is specified for a unit, vibration isolator
literature shall be included containing catalog cuts and
certification that the isolation characteristics of the isolators
provided meet the manufacturer's recommendations. Data shall be
submitted for each specified component.
Spare Parts
Spare parts data for each different item of equipment specified.
Posted Instructions
Posted instructions, at least [2] [_____] weeks prior to
construction completion, including equipment layout, wiring and
control diagrams, piping, valves and control sequences, and typed
instructions shall include preventative maintenance procedures,
methods of checking the system for normal and safe operation, and
procedures for safely starting and stopping the system. The
posted instructions shall be framed under glass or laminated
plastic and be posted where indicated by the Contracting Officer.
Verification of Dimensions
A letter, at least [2] [_____] weeks prior to beginning
construction, including the date the site was visited,
conformation of existing conditions, and any discrepancies found.
System Performance Tests