1.3.6
Calculations
The Contractor shall submit calculations for walls, roof, foundations, and
other features for specialty type of construction, along with design data
for lateral forces that may be encountered due to wind loads and seismic
forces
1.3.7
Spare Parts
The Contractor shall submit spare parts data for each different item of
equipment specified, after approval of the drawings and not later than
[_____] months before the date of beneficial occupancy. The data shall
include a complete list of spare parts and supplies, with current unit
prices and source of supply, and a list of the parts recommended by the
manufacturer to be replaced after [1] [and] [3] year[s] of service
1.4
WELDING QUALIFICATIONS
**************************************************************************
NOTE: Where pipeline, structural, or other welding
is required on the same project, tests will be
required accordingly. Testing may be by the coupon
method as prescribed in the welding code or by
special radiographic methods. If the need exists
for more stringent requirements for weldments,
delete the first bracketed statement and the welding
submittal.
**************************************************************************
[Piping shall be welded in accordance with qualified procedures using
performance qualified welders and welding operators. Procedures and
welders shall be qualified in accordance with ASME BPVC SEC IX. Welding
procedures qualified by others, and welders and welding operators qualified
by another employer may be accepted as permitted by ASME B31.1. The
Contracting Officer shall be notified 24 hours in advance of tests and the
tests shall be performed at the work site if practicable. The welder or
welding operator shall apply his assigned symbol near each weld he makes as
a permanent record. Structural members shall be welded in accordance with
Section 05090A WELDING, STRUCTURAL.] [Welding and nondestructive testing
procedures are specified in Section 05093 WELDING PRESSURE PIPING.]
1.5
DELIVERY AND STORAGE
All equipment delivered and placed in storage shall be stored with
protection from the weather, humidity and temperature variation, dirt and
1.6
VERIFICATION OF DIMENSIONS
The Contractor shall become familiar with all details of the work, verify
all dimensions in the field, and shall advise the Contracting Officer of
any discrepancy before performing the work.
PART 2
PRODUCTS
2.1
Each HTW generator (boiler) shall have the capacity indicated when
operating with [_____] degrees C degrees F entering water temperature and
SECTION 15555A
Page 16