Tolerances, and other Technical
Requirements for Weighing and Measuring
Devices
RUBBER MANUFACTURERS ASSOCIATION (RMA)
RMA IP-1
(1989) Conveyor and Elevator Belt Handbook
THE SOCIETY FOR PROTECTIVE COATINGS (SSPC)
SSPC Paint 16
(1982; R 2000) Coal Tar Epoxy-Polyamide
Black (or Dark Red) Paint
SSPC SP 6
(2000) Commercial Blast Cleaning
TUBULAR EXCHANGER MANUFACTURERS ASSOCIATION (TEMA)
TEMA Stds
(1999) Standards of the Tubular Exchange
Manufacturers Association (TEMA)
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
30 CFR 1
Mine Safety and Health Administration;
Establishment and Use of Official Emblem
UNDERWRITERS LABORATORIES (UL)
UL 296
(2003; Rev thru Jan 2004) Oil Burners
UL 726
(1995; Rev thru Jan 2001) Oil-Fired Boiler
Assemblies
UL 795
(1999) Commercial-Industrial Gas Heating
Equipment
1.2
SUBMITTALS
**************************************************************************
NOTE: Submittals must be limited to those necessary
for adequate quality control. The importance of an
item in the project should be one of the primary
factors in determining if a submittal for the item
should be required.
A "G" following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
SECTION 15555A