design to preclude shifting of equipment under operating conditions or
under abnormal conditions that could be imposed upon the equipment.
Foundations shall meet requirements of equipment manufacturer. Grout
equipment mounted on concrete foundations before installing piping.
Concrete shall conform to Army Corps of Engineers Guide Specification
Section [03300N] CAST-IN-PLACE CONCRETE, and grout shall be non-shrinkable
type approved by the Contracting Officer. Install piping in such a manner
so as not to place a strain on equipment.
3.1.2
Welding
**************************************************************************
NOTE: Use of the ASME code or the Federal
Construction Guide Specification section on welding
depends upon the agency's requirements.
**************************************************************************
**************************************************************************
NOTE: Insert appropriate Section number in blank
below.
**************************************************************************
Work shall be in accordance with [the applicable sections of the ASME BPVC
SEC I] [[_____] WELDING] and AWS Z49.1.
3.1.3
Painting
Equipment shall be factory finished to withstand the intended end use
environment in accordance with the specifications for the particular end
item. Field paint equipment not factory finished as specified herein.
Retouch damaged areas of factory-finished equipment on which the finish has
been damaged and then give a complete finish coat to restore the finish to
its original condition. The finish coat shall be suitable for exposure in
the intended end use environment. Spray painting shall comply with OSHA 29
CFR 1910.
3.1.3.1
Cleaning and Application
Remove dirt, rust, oil, and grease by wire brushing and solvent degreasing
prior to application of paint. Apply paint to clean and dry surfaces only.
Where more than one coat of paint is specified, apply the second coat
after the first coat is thoroughly dry. Retouch damaged painting before
applying the succeeding coat. Finished surfaces shall be smooth. The
painting of zinc coated and other corrosion-resistant metal surfaces is not
required unless otherwise specified herein.
3.1.3.2
Smoke Flues, Boiler Casing, and Draft Ducts
In unfinished areas, paint smoke flues, boiler casing, and black steel
draft ducts with heat-resisting aluminum paint, two coats on the inside of
flues and ducts and one coat on the outside, each coat to a minimum dry
film thickness of 0.025 mm one mil applied directly to clean bare metal
surfaces. Paint exposed surfaces of protective metal covering over
insulation, including zinc-coated surfaces, with two coats of
heat-resisting black paint to a minimum dry film thickness of 0.05 mm two
mils applied directly to the clean bare metal surfaces. Do not paint
zinc-coated ducts.
SECTION 15516N