operating
load and load swings. Show that substantially identical
equipment
of comparable capacity, within 20 percent, has been successfully
installed
and operated in not less than three installations under similar
operating
conditions for a period of not less than 2 years.
1.5.2
Start-Up and Installation Engineer
Provide the services of a qualified engineer or technician for start-up and
tests and installation of equipment as specified below. More than one
engineer or technician may be employed based on the types of specific
equipment. One engineer or technician appointed by the Contractor shall
supervise and be responsible for the overall installation, start-up, test,
and checkout of systems.
1.5.3
Qualifications of Engineer
Submit a printed certified qualification resume of the engineer or
technician. The engineer's or technician's resume shall list applicable
experience related to installation, start-up, and testing of equipment and
applicable factory training and education. Qualifications require the
engineer to have supervised two installations of similar size and type
which are operating satisfactorily. If more than one engineer or
technician is employed, provide a certified resume for each one indicating
their specific specialty and item of work.
1.5.4
Installation
**************************************************************************
NOTE: Delete this paragraph for boilers under 2930
kW 10,000,000 Btu/hr capacity.
**************************************************************************
Provide an installation engineer or technician to install and supervise the
controls. Provide the technician or engineer until the installation of
equipment is coordinated and checkout completed.
1.5.5
Start-Up Plan
Submit a written schedule with dates of start-up tests, installation, and
checkout of equipment.
1.5.6
Start-Up and Test
Start-up and test engineer or technician shall be approved by the
manufacturer of the specific piece of equipment including boiler, boiler
and test engineer or technician shall remain on the job until the unit has
been in successful operation for [_____] days, and has been accepted by the
Contracting Officer.
1.5.7
Start-Up Certification
After installation of equipment, the engineer or technician shall submit a
signed certificate or certified written statement that the equipment is
installed in accordance with the manufacturer's recommendations.