(a)
Maximum continuous rating of boiler no. 1 [_____] kg/s lb/hr
(b)
Maximum continuous rating of boiler no. 2 [_____] kg/s lb/hr
[(c) Maximum continuous rating of boiler no. 3 [_____] kg/s lb/hr]
[(d) Maximum continuous rating of boiler no. 4 [_____] kg/s lb/hr]
(7)
Coal analysis
(a) Ash
[_____] percent
(b) Carbon
[_____] percent
[_____] percent
(d) Sulfur
[_____] percent
(e) Moisture
[_____] percent
[_____] percent
(g) Oxygen
[_____] percent
(8)
Ash Analysis
(a)
Carbon
[_____] percent
(b)
Calcium
[_____] percent
1.4.1.11
Ash Handling System (Pneumatic)
a.
Capacity:
(1) Ash handling system: Estimated capacities at maximum plant
output are listed below; ash handling system capacity shall be
sized for twice the amounts listed.
[_____] Mg tons per hour for fly ash
[_____] Mg tons per hour for bottom ash
[_____] Mg tons per hour in bucket elevator leaving the boiler
house (minimum).
(2) Ash silo: Storage capacity of ash silo is specified in the
paragraph entitled "Ash Storage Silo."
(3)
Rotary unloader:
[_____] Mg tons per hour.
b.
General Data
(1)
Available water pressure:
[_____] kPa (gage) psig
(2)
Available air pressure:
[_____] kPa (gage) psig
(3)
Seismic zone:
[_____]
(4)
Wind velocity (gusts):
[_____] km/hr mph
(5)
Altitude of plant:
[_____] m ft
SECTION 15502N
Page 32