3.1.3.2
Painting
Unless specified otherwise, paint pipe hangers, structural supports, pipe
and pipe fittings, conduit and conduit fittings, air grilles, pipe
coverings, insulation, and metal surfaces associated with mechanical and
electrical equipment including zinc-coated steel ducts as specified in
Section 09900 PAINTS AND COATINGS. Zinc-coated steel duct in unpainted
areas shall not be painted. Apply a protective coating to piping to be
insulated, except zinc-coated and copper pipe, prior to installing
insulation.
3.1.3.3
Boilers
After erecting and testing boilers, clean as necessary exposed surfaces of
the boiler normally painted in commercial practice to remove grease, coal
dust, flyash and other foreign matter and finish with one coat of aluminum
heat resisting paint applied to minimum dry film thickness of 0.025 mm one
mil.
3.1.3.4
Vertical Fuel Oil Tank
Clean interior surfaces to bare metal in accordance with SSPC SP 10. Clean
to bare metal by powered wire brushing or other mechanical means surfaces
that cannot be cleaned satisfactorily by blasting. Wash members which
become contaminated with rust, dirt, oil, grease, or other contaminants
with solvents until thoroughly clean. Remove weld backing plates prior to
blast cleaning; when left in place, round off corners prior to blast
cleaning and coating. Tanks shall be internally coated in accordance with
Section 09970 INTERIOR COATINGS FOR WELDED STEEL PETROLEUM FUEL TANKS.
3.1.3.5
Surfaces Not to be Painted
Unless specified otherwise, do not paint equipment having factory applied
permanent finish, switchplates and nameplates, motor starters, and concrete
foundations.
3.1.4
INSULATION
Insulate mechanical equipment, systems and piping as specified in Section
15080 THERMAL INSULATION FOR MECHANICAL SYSTEMS.
3.2
FIELD QUALITY CONTROL
Provide labor, equipment, test apparatus and materials required for
preparation and performance of tests and inspections specified to
compliance with contract requirements. During start up and during tests,
ensure that factory trained engineers or technicians employed by the boiler
manufacturer and system suppliers or manufacturers of such components as
the boiler, burner, forced draft fan, feedwater treatment equipment, and
adjustment, and testing of the individual components and systems. Furnish
a detailed written record of test conditions, test procedures, field data,
and start up and operational performance of the entire heating plant to the
Contracting Officer before the Contractor's operational and test personnel
leave the site. The Government will furnish, if available, water,
electricity and fuel for the tests, except fuel required for retesting.
The Contractor shall rectify defects disclosed by tests and retest
equipment. The Contractor's boiler plant personnel shall be experienced in