The test supervisor shall certify performance by test to be in
compliance with specifications.
SD-07 Certificates
Work plan
Factory test procedures
Factory testing certification
Qualifications of field supervisors
Field test procedures
Training material
Year 2000 (Y2K) Compliance Warranty; G
Air compressor system
Air compressor system installation
SD-10 Operation and Maintenance Data
**************************************************************************
NOTE: Obtain approval of equipment with proprietary
maintenance requirements from the appropriate
contracts office.
**************************************************************************
Submit in accordance with Section 01781 OPERATION AND
maintenance and repair and shall contain no evidence that
proprietary maintenance arrangements with the manufacturer will be
necessary. Compressors which will require proprietary maintenance
arrangement with the manufacturer require Government review and
approval. The compressors may be disapproved if circumstances do
not justify approval of compressors with limited availability of
maintenance.
SD-11 Closeout Submittals
Submit text.
1.5
QUALITY ASSURANCE
1.5.1
Work Plan
Submit a written schedule of dates of installation, start-up, checkout, and
test of equipment.
1.5.2
Factory Testing Certification
Submit a statement that the air compressor factory is equipped to perform
SECTION 15215N
Page 9