1.5.4
Training Material
Submit a detailed training program syllabus for training of government
personnel, including instructional materials at least three weeks prior to
start of tests.
1.5.5
System Installation
Submit certification of air compressor system performance conforming to
ASME PTC 10 and ASME BPVC SEC VIII D1. Submit certification of proper
system installation in accordance with paragraph entitled "Supervision."
1.5.6
Air Compressor System
Submit operation and maintenance data in accordance with Section 01781
for maintenance and repair and shall contain no evidence that proprietary
maintenance arrangements with the manufacturer will be necessary.
Compressors which will require proprietary maintenance arrangement with the
manufacturer require Government review and approval. The compressors may
be disapproved if circumstances do not justify approval of compressors with
limited availability of maintenance.
1.6
SAFETY
Construct all components of the unit in accordance with the requirements of
OSHA 29 CFR 1910.219. Requirements include shaft coupling guards as
specified in Section 15050N BASIC MECHANICAL MATERIALS AND METHODS, thermal
insulation and jacketing with manufacturer standard covering or aluminum
sheet of all surfaces at 52 degrees C 125 degrees F and higher within a
height of 2.10 m 7 feet from floor level, and use of electrical safety
devices. Thermal insulation, furnished by equipment manufacturer, shall
conform to ASTM C 553, Type I (flexible resilient), Class B-5 (up to 204
degrees C 400 degrees F), 32 kg/m3 2 pcf nominal. Cement insulation to
surface with MIL-A-3316, Class 2, adhesive and fasten with 16 gage wire
bands at maximum 405 mm 16 inches on center spacing. Cover insulation with
ASTM B 209M ASTM B 209 sheet aluminum jacket. The thermal insulation is
required for unit with separate intercooler and aftercooler units.
1.7
EQUIPMENT ARRANGEMENT
Arrangement selected shall maintain 0.9 m 3 foot clearance for access
passage and 1.20 m 4 foot clearance for personnel to operate equipment.
There are substantial physical and connection point differences among the
Contractor shall be responsible for selecting equipment and submitting
arrangement drawings covering required changes for approval by the
Contracting Officer. Changes from the equipment arrangement shown on the
contract drawings shall be performed by the Contractor at no additional
cost to the Government.
1.8
ELECTRICAL REQUIREMENTS
Comply with the requirements of Section 16402 INTERIOR DISTRIBUTION SYSTEM,
[and [_____]].
1.9
SUPERVISION
The Contractor shall obtain the services of a qualified engineer or
SECTION 15213N
Page 10