Backflow Preventer; G
Annotate descriptive data to show the specific model, type, and
size of each item.
SD-05 Design Data
Sprinkler system design; G
Submit [computer program generated] hydraulic calculations to
Submit name of software program used.
SD-06 Test Reports
Preliminary tests on piping system; G
SD-07 Certificates
Qualifications of installer; G
Year 2000 (Y2K) Compliance Warranty
SD-10 Operation and Maintenance Data
Alarm valves, Data Package 3; G
Excess pressure pump, Data Package 3; G
Backflow preventer, Data Package 3; G
Submit in accordance with Section 01781 OPERATION AND
MAINTENANCE DATA.
SD-11 Closeout Submittals
As-built drawings of each system; G
1.6
QUALITY ASSURANCE
1.6.1
Qualifications of Installer
Prior to installation, submit data showing that the Contractor has
successfully installed systems of the same type and design as specified
herein, or that Contractor has a firm contractual agreement with a
subcontractor having such required experience. Data shall include names
and locations of at least two installations where the Contractor, or the
subcontractor referred to above, has installed such systems. Indicate type
and design of each system and certify that each system has performed
satisfactorily in the manner intended for not less than 18 months.
Qualifications of System Technician: Installation drawings, shop drawing
and as-built drawings shall be prepared, by or under the supervision of, an
individual who is experienced with the types of works specified herein, and
is currently certified by the National Institute for Certification in
Engineering Technologies (NICET) as an engineering technician with minimum
SECTION 13930N
Page 9