f.
g. Operation of each initiating device circuit connected directly to a
h.
Operation of all supervisory features.
i.
Operation of all features of each base receiving/control network.
j. Test all functions of the computer-aided dispatch (CAD) system to
verify proper programming and operation.
3.4.2
Final Acceptance Test
The system shall have been in service for at least 30 days prior to the
final inspection. Notify the Contracting Officer in writing when the system
is ready for final acceptance tests. Notification shall be at least 15
days prior to the requested date of the final acceptance test. The system
shall be considered ready for such testing only after all necessary
preliminary tests have been made, all deficiencies found have been
corrected to the satisfaction of the equipment manufacturer's technical
representative, and written certification to that effect from the
manufacturer's technical representative has been submitted to the
Contracting Officer. The system shall be tested for approval in the
presence of representatives of the manufacturer, the Contracting Officer,
and the [EFD] [EFA] Fire Protection Engineer. Furnish all instruments,
labor, and materials required for the tests. The technician and
electrician who supervised the installation shall be present throughout
the tests. Any deficiencies found shall be corrected and the system
paragraph entitled "Tests During Installation" shall be repeated as
directed by the [EFD] [EFA] Fire Protection Engineer during conduct of
final acceptance tests. Furnish all necessary appliances, equipment,
instruments, devices, and personnel for this test. Furnish a minimum of
three portable two-way radios operating on the same non-Government
3.5
ADDITIONAL TESTS
When deficiencies, defects or malfunctions develop during the tests
required, all further testing of the system shall be suspended until proper
adjustments, corrections or revisions have been made to assure proper
performance of the system. If these adjustments, corrections or revisions
require more than a nominal delay, the Contracting Officer shall be
notified when the additional work has been completed to arrange a new final
inspection and test of the fire alarm system. All tests required shall be
repeated prior to final acceptance, unless directed otherwise. The
all costs incurred by the Government as a result of reinspection and
retesting of the system.
3.6
INSTRUCTION OF GOVERNMENT PERSONNEL
3.6.1
Instruction of Operating Personnel
**************************************************************************
NOTE: Consult the Federal Fire Chief regarding the
number of shifts and number of personnel to be
SECTION 13853N
Page 38