date. Activation of a watchtour station shall cause a corresponding green
LED on the watchtour panel to extinguish. Reset shall occur when the last
green LED is extinguished. Once all stations in the area have been
activated, regardless of order but within the time frame, a "tour complete"
green LED on the watchtour panel shall illuminate and a signal shall be
sent to the system printer to print "tour complete," location, time and
date. Pressing the "reset" momentary action switch shall cause all LEDs
associated with the watchtour system to turn off. Activation of a
watchtour station after a "reset" action but before a "start" action, shall
have no effect. Alarm shall be generated on fifteen minute interval at
watchtour control panel to alert guard to begin watchtour.
1.3
SUBMITTALS
**************************************************************************
NOTE: Submittals must be limited to those necessary
for adequate quality control. The importance of an
item in the project should be one of the primary
factors in determining if a submittal for the item
should be required.
A "G" following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Watchtour system
SECTION 13799
Page 5