shall be obtained from the Government before proceeding with the next phase
of testing. Original copies of all data produced during predelivery,
performance verification and endurance testing, shall be turned over to the
Government at the conclusion of each phase of testing, prior to Government
approval of the test.
3.4.2
Predelivery Testing
a. The Contractor shall assemble the test system as specified, and perform
tests to demonstrate that performance of the system complies with specified
requirements in accordance with the approved predelivery test procedures.
The tests shall take place during regular daytime working hours on
weekdays. Model numbers of equipment tested shall be identical to those to
be delivered to the site. Original copies of all data produced during
predelivery testing, including results of each test procedure, shall be
delivered to the Government at the conclusion of predelivery testing, prior
to Government approval of the test. The test report shall be arranged so
that all commands, stimuli, and responses are correlated to allow logical
interpretation.
b.
Test Setup: The predelivery test setup shall include the following:
1)
All central station equipment.
2) At least 1 of each type DTS link, but not less than 2 links, and
associated equipment to provide a fully integrated system.
3) The number of local processors shall equal the amount required by
the site design.
4)
At least 1 of each type sensor used.
5) Enough sensor simulators to provide alarm signal inputs to the
system equal to the number of sensors required by the design. The
alarm signals shall be manually or software generated.
6)
At least 1 of each type of terminal device used.
7) At least 1 of each type of portal configuration with all facility
interface devices as specified or shown.
8) Equipment as specified in Section 16751A CLOSED CIRCUIT TELEVISON
SYSTEMS when required.
9) The Contractor shall prepare test procedures and reports for the
predelivery test, and shall deliver the predelivery test procedures to
the Government for approval. The final predelivery test report shall
be delivered after completion of the predelivery test.
3.4.3
Contractor's Field Testing
The Contractor shall calibrate and test all equipment, verify DTS
operation, place the integrated system in service, and test the integrated
system. Ground rods installed by the Contractor shall be tested as
specified in IEEE Std 142. The Contractor shall deliver a report
describing results of functional tests, diagnostics, and calibrations,
including written certification to the Government that the installed
complete system has been calibrated, tested, and is ready to begin
performance verification testing. It is recommended that the Contractor