1.6.3
Regulatory Requirements
Provide only UL listed IDS equipment except for exterior IDS sensors,
access control, and closed-circuit television (CCTV) components.
1.6.4
IDS Operational Test Plan
Submit at least 30 days prior to commencement of formal operational
testing. Include detailed procedures for operational testing of each IDS
component and subsystem, and for performance of an integrated system test.
1.6.5
User's Software Data
Submit for approval not later than 30 days prior to formal operational
testing or instruction to Government personnel on IDS software, whichever
is earlier. IDS software shall be documented in the user's manual.
PART 2
PRODUCTS
2.1
IDS SUBSYSTEMS
Provide a complete integrated IDS consisting of the following major
subsystems:
a.
Detection
[b.
Basic automated access control]
c.
Communications
[d.
Closed-circuit television (CCTV)]
e.
Alarm reporting and display
f.
Power
2.2
INTEGRATED SYSTEM FUNCTIONAL REQUIREMENTS
Ensure that IDS is fully integrated with physical security and other
elements of the overall facility security system. Provide specific
subsystem consisting of the following:
a.
Detection subsystem: Sensors to detect intrusion attempts [and
provide means to indicate a duress condition].
[b.
monitor and control personnel movement through normal access
routes in and out of the facility and between protected areas
within the facility.]
c.
pertinent data is transferred from point of origin to point where
appropriate actions can be taken. [Provide redundant
[d.
CCTV subsystem: Electronic devices required to provide visual
assessment of IDS alarms [at two separate locations].]
e.
Alarm reporting and display subsystem:
Electronic devices to
SECTION 13703N
Page 15