[3.6.10
Methods for Asphaltic Wrap
Removal or disturbance of pipeline asphaltic wrap shall be performed using
wet methods.]
3.6.11
Class I Asbestos Work Response Action Detail Sheets
**************************************************************************
NOTE: Remove items in this subparagraph that do not
apply.
**************************************************************************
The following Class I Asbestos Work Response Action Detail Sheet is
specified on Table 1 for each individual work task to be performed:
a.
Troweled Wall Plaster on Masonry:
See Sheet 32
b.
Troweled Wall Plaster on Stud Wall:
See Sheet 33
c.
Troweled Ceiling Plaster on Structural Substrate:
See Sheet 35
d.
Troweled Ceiling Plaster on Hung Ceiling:
See Sheet 36
e.
Acoustical Wall Plaster on Masonry:
See Sheet 42
f.
Acoustical Ceiling Plaster (Non-Asbestos Substrate):
See Sheet 44
g.
Asbestos Decorative Paint on Plaster:
See Sheet 46
h.
Asbestos-contaminated Masonry for Masonry Chimney:
See Sheet 50
i.
Asbestos-contaminated Masonry Wall or Thermal Insulation:
See
Sheet 51
j.
Fireproofing or Thermal Surface Insulation:
See Sheet 68
k.
Acoustical Ceiling Insulation:
See Sheet 70
l.
Exterior Asbestos Stucco:
See Sheet 79
m.
Duct Insulation: Air circulation is not permitted in ductwork
while abatement work is in progress. See Sheet 101. The HVAC
system shall be isolated or inoperative and locked out of service
prior to removal of duct insulation. Air circulation is not
permitted in ductwork during abatement work.
n.
Pipe Insulation (Using a Glovebag):
See Sheet 87
o.
See Sheet
88
p.
See Sheet 89
q.
Storage Tank and Boiler Breeching Insulation: See Sheet 93.
Storage tanks and boilers shall be valved off an allowed a
suffiecient amount of time to cool down prior to abatement work.
Insulation shall be sprayed with a mist of amended water or
removal encapsulant. Amended water or removal encapsulant shall
SECTION 13280A
Page 41