Pressure differential recordings.
SD-07 Certificates
Manufacturer's certifications showing compliance with ANSI Z9.2
for:
a.
Vacuums.
b.
Water filtration equipment.
c.
Ventilation equipment.
d.
Other equipment required to contain airborne asbestos fibers.
Encapsulants[; G][; G, [_____]]
Certificates stating that encapsulants meet the applicable
specified performance requirements.
Medical Surveillance Requirements
Required medical certification and the Physician's written
opinion.
1.4
DESCRIPTION OF WORK
**************************************************************************
NOTE: Review the Notes under PART 1 GENERAL. For
each individual ACM abatement work task, consult
with the customer, review EP 1110-1-11 and enter the
required work task data on Table 1, at the end of
this Section, as described in the Notes section of
the Table. There will be one data sheet for each
abatement work task. Attach to each work task data
sheet the selected Response Action Detail Sheet and
its referenced Set-up Detail Sheets. Select
applicable bracketed items in this section.
Discovery of Unexpected Asbestos: Suspect asbestos
containing material that is discovered during
demolition (in particular buildings constructed no
later than 1980), which was previously inaccessible,
must be sampled and analyzed for its asbestos
content. The designer should anticipate additional
sampling and analysis. The number of additional
samples should be based on the extent of demolition
and previous survey data. Insert the number of bulk
samples anticipated in the bracket in paragraph
Unexpected Discovery of Asbestos. Sampling
activities undertaken to determine the presence of
additional ACM should be conducted by personnel who
have successfully completed the EPA Model
SECTION 13280A
Page 14