Submit test reports for specified tests under paragraph entitled
"Source Quality Control." Test reports shall contain as minimum,
date, project title and location, location of signal source,
dynamic range, noise floor, SA (required and actual), any repair
SD-07 Certificates
Certification of welders; G
Test compliance of HEMP shielded door; G
SD-08 Manufacturer's Instructions
Test plan; G
Welding procedure; G
SD-10 Operation and Maintenance Data
**************************************************************************
NOTE: Designer should consult with the Engineering
Service Center, Code 065, on DNA-TR-91-87 HM/HS
Manual.
**************************************************************************
Hardness Maintenance and Hardness Surveillance (HM/HS) Manual,
Data Package 3; G
Submit in accordance with Section 01781 OPERATION AND
MAINTENANCE DATA.
SD-11 Closeout Submittals
Final acceptance test
EM shielded door tests
**************************************************************************
NOTE: Check with using agency, if test report needs
to be classified [secret] [top secret].
**************************************************************************
Submit test reports for specified tests under paragraph entitled
"Field Quality Control." Test reports shall contain as a minimum,
date, project title and location, location of signal source,
dynamic range, noise floor, SA (required and actual), any repair
[Test report is classified [secret] [top secret] [_____],
therefore, the independent tester shall have the necessary
security clearance]. Log the test data for each test point on the
form as the test progresses. Have the witness sign the data form
at the end of each day.