drawings, and not later than [3] [_____] months prior to the date of work
completion. The data shall include a complete list of parts and supplies,
with current unit prices and source of supply.
PART 2
PRODUCTS
2.1
MATERIALS
Materials and equipment shall conform to the following requirements.
2.1.1
Steel Plates, Shapes and Bars
ASTM A 36/A 36M.
2.1.2
Pipe
Piping shall be furnished and installed as indicated and be in accordance
with the applicable standard specification.
2.1.2.1
Steel Pipe
ASTM A 53/A 53M, all pipe sizes.
a.
ASTM A 707/A 707M.
b.
Slip Joints:
AWWA C200.
c.
Mechanical Joints:
AWWA C200.
d.
Welded Joints:
AWS D1.1/D1.1M.
e.
Bolts:
ASTM A 307, Grade B.
f.
Fittings:
ASTM A 420/A 420M.
2.1.2.2
Ductile-Iron Pipe
AWWA C115, all pipe sizes.
a.
Flanged Pipe:
AWWA C115 with ASME B16.1, Class 125 flanges.
b.
Rubber-Gasket Joints:
AWWA C111.
c.
Fittings:
AWWA C110.
d.
Push-On Joints:
AWWA C151.
e.
Bolts and Nuts:
ASTM A 307, Grade B.
f.
Coatings and Linings:
Buried piping shall have standard
bituminous coating.
2.1.2.3
Polyvinyl Chloride (PVC) Pipe and Fittings
PVC pipe and fittings less than 102 mm 4-inch diameter shall be in
accordance with ASTM D 1785 or ASTM D 2241. PVC pipe and fittings 102 mm 4
inch in diameter and larger shall be in accordance with ASTM D 2241 and
shall have push-on joints.
SECTION 11391