1.9.1
Standard Products
Materials and equipment shall be the standard products of a manufacturer
regularly engaged in the manufacture of such products and shall essentially
duplicate items that have been in satisfactory use for at least 2 years
prior to bid opening. Equipment shall be supported by a service
organization that is, in the opinion of the Contracting Officer, reasonably
convenient to the site.
1.9.2
Nameplates
Each major item of equipment shall have the manufacturer's name, address,
type or style, model or serial number, and catalog number on a plate
secured to the item of equipment. Each piece of equipment shall bear the
approval designation and the markings required for that designation.
Valves shall be marked in accordance with MSS SP-25 and shall bear a
securely attached tag with the manufacturer's name, catalog number and
valve identification permanently displayed.
1.9.3
Safety Requirements
Belts, chains, couplings, and other moving parts shall be completely
enclosed by guards, to prevent accidental personal injury, in accordance
with 29 CFR 1910, Subpart O, Machinery and Machine Guarding. Guards shall
be removable and arranged to allow access to the equipment for maintenance.
Thermal insulation shall enclose high temperature components to prevent
ignition of combustible materials and to preclude personnel contact.
1.9.4
Verification of Dimensions
After becoming familiar with all details of the work, the Contractor shall
verify all dimensions in the field, and shall advise the Contracting
Officer of any discrepancy before performing the work.
1.10
SEQUENCING AND SCHEDULING
**************************************************************************
NOTE: Testing of the thermal oxidation system
should be concurrent with the start of gas flow from
the landfill, vapor extraction system, or other
source. Section 01450A CHEMICAL DATA QUALITY
CONTROL should be included even if the project is
not concerned with HTRW.
**************************************************************************
Installation of the thermal oxidizer shall be complete and the system
operational prior to completion of the [gas collection system] [vapor
extraction system] [landfill cap]. Point source release of untreated
off-gas shall be avoided to the maximum extent consistent with completion
of the contract. Sampling and analyses to demonstrate system performance
and emission compliance shall be performed in accordance with Section 01450A
CHEMICAL DATA QUALITY CONTROL.
1.11
AUXILIARY EQUIPMENT AND SPARE PARTS
**************************************************************************
NOTE: Include items needed for future maintenance
and repair, items that might be difficult to obtain
and spare parts needed to ensure continued operation
SECTION 11378
Page 16