submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Layout[; G][; G, [_____]]
Installation[; G][; G, [_____]]
Drawings showing fabrication methods, assembly, accessories,
Drawings shall indicate clearances required for maintenance and
operation and shall also contain complete wiring and schematic
diagrams, equipment layout, dimensions, templates and directions
for the installation of anchor bolts and other anchorages and any
other details required to demonstrate that the system has been
coordinated and will properly function as a unit.
SD-03 Product Data
Equipment[; G][; G, [_____]]
Manufacturer's descriptive data, technical literature, and
catalog cuts. Submittal shall include: design calculations
relevant to the type of system proposed indicating removal
performance including dose; nominal average intensity within each
reactor; UV density; theoretical retention time of effluent within
SECTION 11376
Page 5