USACE / NAVFAC / AFCESA
UFGS-09200A (December 2003)
---------------------------
Preparing Activity: USACE
Superseding
UFGS-09200A (June 1997)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated 23 June 2005
Latest change indicated by CHG tags
**************************************************************************
SECTION 09200A
LATHING AND PLASTERING
12/03
**************************************************************************
NOTE: This guide specification covers the
requirements for plasterwork for studs, furring and
Comments and suggestions on this guide specification
are welcome and should be directed to the technical
proponent of the specification. A listing of
technical proponents, including their organization
designation and telephone number, is on the Internet.
Recommended changes to a UFGS should be submitted as
a Criteria Change Request (CCR).
Use of electronic communication is encouraged.
Brackets are used in the text to indicate designer
choices or locations where text must be supplied by
the designer.
This guide specification includes tailoring options
for gypsum plaster, and cement plaster. Selection
or deselection of a tailoring option will include or
exclude that option in the section, but editing the
resulting section to fit the project is still
required.
**************************************************************************
PART 1
GENERAL
**************************************************************************
NOTE: Locations and details of trim items for
plasterwork will be indicated on the drawings. Trim
items that may be required to complete the
plasterwork in a workmanlike manner will be
specified.
Plaster may be applied directly to masonry, but
furring and lath are required for plaster finish on
SECTION 09200A
Page 4