Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Sliding fire doors; G, [_____]
Submit drawings for all sliding fire doors. Show types, sizes,
location, metal gages, hardware, installation details, and other
details of construction.[ For motor-operated doors, include
supporting brackets for motors, location, type, ratings of motors,
and safety devices.]
SD-03 Product Data
Sliding fire doors; G, [_____]
Electrical Work; G, [_____]
SD-08 Manufacturer's Instructions
Sliding fire doors
SD-10 Operation and Maintenance Data
Sliding fire doors, Data Package 2; G, [_____]
Submit in accordance with Section 01781 OPERATION AND
1.3
DELIVERY AND STORAGE
Deliver fire doors to the job site wrapped in a protective covering bearing
manufacturer's name and brand. Store doors in dry locations with adequate
ventilation, free from dust or water, and in such a manner to permit access
for inspection and handling. Handle doors carefully to prevent damage.
Remove damaged items that cannot be restored to like-new condition and
provide new items.
PART 2
PRODUCTS
2.1
SLIDING FIRE DOORS
Shall conform to NFPA 80, UL 10B, and the requirements specified herein,
and shall be listed (labeled). Provide doors complete with operating
devices, hardware, and accessories.
SECTION 08162
Page 6