(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
SD-07 Certificates
Chain Link Fence
Statement, signed by an official authorized to certify on behalf
of the manufacturer, attesting that the chain link fence and
component materials meet the specified requirements.
SD-10 Operation and Maintenance Data
Gate Operator
[Six] [_____] copies of operating and maintenance instructions,
a minimum of 2 weeks prior to field training. Operating
instructions shall outline the step-by-step procedures required
for system startup, operation, and shutdown. The instructions
shall include the manufacturer's name, model number, service
manual, parts list, and brief description of all equipment and
their basic operating features. Maintenance instructions shall
include routine maintenance procedures, possible breakdowns and
repairs, and troubleshooting guide. The instructions shall
include the general gate layout, equipment layout and simplified
wiring and control diagrams of the system as installed.
[1.3
APPROVAL OF POLYVINYL CHLORIDE-COATED FENCE MATERIALS
Polyvinyl chloride-coated fence materials shall be throughly inspected for
cracking, peeling, and conformance with the specifications by the
Contracting Officer's Representative prior to installation. Any fence
materials rejected by the Contracting Officer's Representative shall be
replaced by the contractor with approved materials at no additional cost to
the Government.]
PART 2
PRODUCTS
2.1
FENCE FABRIC
Fence fabric shall conform to the following:
SECTION 02821A
Page 6