subparagraphs below should be inserted into Section
01270.
**************************************************************************
1.2.1
[Relief Wells]
1.2.1.1
Payment
Payment will be made for costs associated with relief wells, which price
shall constitute full compensation for construction of relief wells. Wells
ordered abandoned by the Contracting Officer before installation of well
screen and riser due to no fault of the Contractor will be paid for at
[_____] percent of the contract unit price per linear meter foot, for Bid
Item No. [_____] "Relief Wells". Wells ordered abandoned by the
Contracting Officer due to no fault of the Contractor shall be paid for at
the full contract unit price for Bid Item No. [_____] "Relief Wells". No
payment will be made for placement or replacement of temporary casings or
repair of damage resulting from Contractor operations. No separate payment
will be made for relief well screen, riser, check valves, gravel pack,
development, backfill, discharge or outfall pipes. No payment will be made
for any wells that, in the opinion of the Contracting Officer, are
abandoned due to Contractor fault or neglect.
1.2.1.2
Measurement
Relief wells will be measured for payment by the linear meter foot of
completed well between ground surface and 300 mm 1 foot below the bottom of
the [well screen][tail pipe]. Wells ordered abandoned by the Contracting
Officer, due to no fault of the Contractor, will be measured for payment.
1.2.1.3
Unit of measure
Unit of measure:
linear meter foot.
1.2.2
[Pump Tests]
1.2.2.1
Payment
Payment will be made for costs associated with pump test, which price shall
constitute full compensation to perform a satisfactory pump test as
specified. No payment will be made for pump test not successfully
completed.
1.2.2.2
Measurement
Pump tests will be measured for payment for each hour, measured to the
nearest 15 minutes, of pump test successfully performed as specified in
paragraph PUMP TEST, and as otherwise directed. Testing time will not
include time required to place and remove testing and pump equipment.
1.2.2.3
Unit of measure
Unit of measure:
per hour.
1.2.3
[Pump Installation/Removal]
1.2.3.1
Payment
Payment will be made for costs associated with installation and removal of
SECTION 02525A
Page 7