ASTM D 5521
(1994; E 1998) Development of Ground-Water
Monitoring Wells in Granular Aquifers
ASTM D 5608
Used at Low Level Radioactive Waste Sites
ASTM F 480
(2002) Thermoplastic Well Casing Pipe and
Ratios (SDR), SCH 40 and SCH 80
U.S. ARMY CORPS OF ENGINEERS (USACE)
COE TR GL-85-3
(1985) Geotechnical Descriptions of Rock
and Rock Masses
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA 600/4-79/020
Water and Wastes
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
49 CFR 172
Information, and Training Requirements
1.2
MEASUREMENT AND PAYMENT
**************************************************************************
NOTE: Separate pay items for test holes and water
wells must be included in the contract.
**************************************************************************
Payment for each specified item will be made at the contract unit price for
that item. Payment will include full compensation for equipment, materials
and labor for drilling; removal and disposal of temporary casing, cuttings,
and drill fluid; preparation of borehole logs; and sample handling,
containers, storage, and testing. Depth, logging, installation, casing,
riser pipe, and well screen shall be measured by linear distance. Payment
will not be allowed for test holes or wells abandoned due to construction
practices not in accordance with this specification, faulty construction
practices or for the convenience of the Contractor.
1.2.1
Test Hole
Compensation for the test hole will be made at the contract unit price and
will include material, equipment, and labor required to drill and perform
tests on the test hole. Depth shall be measured as the total linear
distance between ground surface and bottom of hole. If the total depth of
hole is greater than that specified on the contract for "Test Hole," the
additional depth will be paid for at the contract unit price for
"Additional Test Hole Depth." If the test hole is developed into the
permanent well with no increase in diameter, the Contractor will be
compensated as described below, and separate payment will not be made for
the test hole.
SECTION 02521
Page 6